Most popular

How do you calculate aggregate cubic feet?

How do you calculate aggregate cubic feet?

Manual Calculator

  1. Multiply the length of the area by the width of the area = Square Feet.
  2. Multiply Square Feet by the Depth* = Cubic Feet.
  3. Divide Cubic Feet by 27 = Cubic Yards.
  4. Multiply Cubic Yards by 1.5 = Tons Needed.

How do you calculate aggregate quantity?

How To Calculate Cement, Sand, & Aggregate Quantity In 1 Cubic metre Concrete

  1. Density of Cement = 1440 kg/m3.
  2. Sand Density = 1450-1500 kg/m3.
  3. Density of Aggregate = 1450-1550 kg/m3.

How do you calculate cubic feet of concrete?

To determine how many cubic feet you need for a hole, measure the length, width, and thickness together, all measured in feet. So a 4″ thickness is 4″/12″ or 0.333 feet. The result of this Length x Width x Thickness multiplication is cubic feet.

READ ALSO:   Why do people cut weight in wrestling?

How much aggregate is 1m3 of concrete?

1m3 of concrete is made up of 403Kg of cement, 706Kg of sand, 1,302Kg of aggregate and 240 Litres of water. The mix design process can either be conducted on the basis of charts or experimentally.

How much sand do I need for 1m3 of concrete?

Typically, 1m3 of concrete is made up of 350Kg of cement, 700Kg of sand, 1,200Kg of chippings and 150 Litres of water. The mix design process can either be conducted on the basis of charts or experimentally. These methods are based on achieving the maximum density of concrete..

How do you calculate 1m3 concrete cement?

Thus, the quantity of cement required for 1 cubic meter of concrete = 0.98/0.1345 = 7.29 bags of cement. The quantities of materials for 1 m3 of concrete production can be calculated as follows: The weight of cement required = 7.29 x 50 = 364.5 kg. Weight of fine aggregate (sand) = 1.5 x 364.5 = 546.75 kg.

READ ALSO:   Which company Colour pencils is best?

How do you calculate sand in 1m3 concrete?

The quantities of materials for 1 m3 of concrete production can be calculated as follows: The weight of cement required = 7.29 x 50 = 364.5 kg. Weight of fine aggregate (sand) = 1.5 x 364.5 = 546.75 kg. Weight of coarse aggregate = 3 x 364.5 = 1093.5 kg.

How to find cement sand and aggregate quality in 1 cubic meter concrete?

Now we start calculation for find Cement, Sand and Aggregate quality in 1 cubic meter concrete For Calculate in CFT (Cubic Feet) = 8 x 1.225 = 9.8 Cubic Feet Sand= (1.5/5.5) x 1.54 = 0.42 m3 ∴ 1.5 is a part of Sand, 5.5 is sum of ratio

How do you calculate quantity of aggregate in cubic feet?

Quantity of Aggregate in cubic feet = Nos of cement bags × Volume of one bag cement in cft × Ratio of aggregate Let us consider water cement ratio = 0.45 Water requirement for 1 bag cement = 0.45 x 0.0347 (Volume of 1 bag cement = 0.0353 cum)

READ ALSO:   Is BU better than UCI?

How do you calculate the volume of a concrete slab?

For Calculate in CFT (Cubic Feet) = 8 x 1.225 = 9.8 Cubic Feet CALCULATION FOR SAND QUANTITY Consider volume of concrete = 1m3 Dry Volume of Concrete = 1 x 1.54 = 1.54 m3

What is the quantity of sand in cubic feet?

Quantity of Sand in cum = 1.54 / 7 × 2 (where 2 is the ratio of sand ) Quantity of Sand in kg = 0.44 × 1450 (density of sand = 1450 to 1500 kg/m3) Quantity of Sand in cubic feet = 1.54 / 7 × 2 × 35.314 (1 cum = 35.314 cft ) Quantity of Sand in cubic feet = Nos of cement bags x Volume of one bag cement in cft × Ratio of sand